HDD DRILL CONSTRUCTION PROGRESS

HDD DRILL CONSTRUCTION PROGRESS

Ngày đăng: 13-03-2021

1,602 lượt xem

TABLE OF CONTENTS

1.0 GENERAL INTRODUCTION

1.1 PROJECT OVERVIEW

1.2 GENERAL INFORMATION ABOUT THE WORKS

1.3 MATERIAL PURPOSE

1.4 LEGAL DOCUMENTS

1.5 DEFINE

2.0 PREPARATION OF CONSTRUCTION

3.0 CONSTRUCTION STAFF

4.0 CONSTRUCTION EQUIPMENT

5.0 TEMPORARY WORKS FOR CONSTRUCTION

6.0 DRILL CONSTRUCTION PROGRESS

7.0 CONSTRUCTION MATERIAL

8.0 DEEP AND SPACE TO UNDERGROUND WORKS

9.0 CONSTRUCTION METHODS AND DRILLING TECHNICAL SOLUTIONS

9.1 SURVEY

9.2 MACHINE EQUIPMENT AND HUMAN RESOURCE

9.3 PREPARATION OF DRILL work

9.4 WORKS DRILL GUIDE

9.5 DRILL SIZES EXPANDs

9.6 DRAINING WORKS

9.7 CLEANING AND RETURNING WORK

10.0 MEASURES OF SAFETY, ENVIRONMENT, SAFETY AND SECURITY OF THE Site

10.1 GENERAL RULES

10.2 SECURITY

10.3 ENVIRONMENTAL SANITATION

10.4 EXPLOSION OF FIRE PREVENTION, INTERNAL TRANSPORT SAFETY

10.5 LABOR SAFETY

1.0 GENERAL INTRODUCTION

1.1 PROJECT OVERVIEW

1.2 GENERAL INFORMATION ABOUT THE WORKS

Project name: Construction of pipeline network

Under the project: Darco Ba Lai Clean Water Factory.

Type of project, grade of project: Group B project, Water pipe work, Level II.

Location: Tan My commune, Ba Tri district, Ben Tre province.

1.3 MATERIAL PURPOSE

The purpose of this document is to provide a method for the Contractor to perform and control the construction of the pipeline network at the locations as attached in the attached drawing, under the project "DARCO BA LAI CLEAN WATER FACTORY".

1.4 LEGAL DOCUMENTS

- Law on Construction No. 50/2014 / QH 13 dated June 18, 2014 of the 13th National Assembly session;

- Law on Environmental Protection No. 55/2014 / QH13 passed on 23/06/2014 takes effect from 01/01/2015 of the 13th National Assembly session 7;

- Decree No. 59/2015 / ND-CP dated June 18, 2015 of the Government on management of construction investment projects;

- Decree No. 42/2017 / ND-CP dated April 5, 2017 of the Government amending and supplementing a number of articles of Decree No. 59/2015 / ND-CP dated June 18, 2015 of the Government on construction investment project management;

- Decree No. 46/2015 / ND-CP dated 12/5/2015 of the Government on quality management and construction maintenance;

- Decree No. 11/2010 / ND-CP dated February 24, 2010 of the Government regulating the management and protection of road traffic infrastructure;

- Circular No. 50/2015 / TT-BGTVT dated September 23, 2015 of the Ministry of Transport on "Guiding the implementation of a number of articles of Decree No. 11/2010 / ND-CP dated February 24, 2010 .

- Pursuant to Decree No. 32/2015 / ND-CP dated March 25, 2015 on construction cost management;

1.5 DEFINE

Investor

:

DARCO BA LAI WATER SUPPLY CO.LTD

Consulting

:

ARTELIA VIET NAM CO.LTD

Project

:

DARCO BA LAI CLEAN WATER FACTORY

Package

:

Design, Fabrication and Construction, Installation

2.0 PREPARATION OF CONSTRUCTION

The preparation work was done according to the construction of the whole pipeline.

3.0 CONSTRUCTION STAFF

List of personnel involved in underground drilling construction:

STT

First and last name

Date of birth

ID number

Home town

Position

1

Nguyen Văn Thanh

6/5/1970

038070006601

Thanh Hoa

Director – commandant

2

Tran Anh Tuan

13/06/1972

273136899

Ha Tinh

Deputy commander

3

Đang Xuan Dien

7/10/1961

024716077

Nghe An

Deputy commander

4

Đang Minh Nhut

1986

025748413

Đong Thap

Deputy commander

5

Đo Thi Kim My

17/05/1997

291141831

Tay Ninh

Secretary

6

Nguyen Ngoc Thanh

20/03/1992

173754257

Thanh Hoa

Captain

7

Nguyen Tien Long

27/06/1998

175023765

Thanh Hoa

Skill

8

Tran Manh Sung

30/09/1976

033076001982

Hung Yen

Drive the drill

9

Au Le Hai

1973

312381178

Bac Giang

Drive the drill

10

Duong Van Minh

19/04/1987

281286071

Nghe An

Accessories Drilling

11

Nguyen Thanh Hung

03/09/1972

038072003565

Thanh Hoa

Accessories Drilling

12

Nguyen Van Sang

12/081968

261623922

Thai Nguyen

Accessories Drilling

13

Vo Xuan Oanh

30/10/1965

181484282

Nghe An

Accessories Drilling

14

Đoan Van Đong

1/12/1996

251064894

Lam Đong

Accessories Drilling

15

Duong Van Đai

10/10/1999

187766885

Nghe An

Accessories Drilling

16

Nguyen Ngoc Noi

20/11/1970

172156753

Thanh Hoa

Accessories Drilling

17

Phan van Truc

20/03/1977

261221690

Thai Nguyen

Accessories Drilling

18

Pham Minh Tuan

19/05/1976

320940871

Ben Tre

Technical staff

19

Đao Minh Tuan

29/08/1995

362427232

Can Tho

Technical staff

20

Nguyen Minh Phung

09/08//1995

301600511

Long An

Technical staff

According to the construction organization chart of the project that has been approved by the investor

4.0 CONSTRUCTION EQUIPMENT

List of construction equipment:

 

STT

Types of machinery

Amount

Own / Rent

Note

1

Crane 40 tons

01

Rent

 

2

Generator 20 kVA

01

Rent

 

3

Excavator 1 m3

02

Rent

 

4

Welding machine A300

5

Own

 

5

Grinding and cutting machine Ø150

4

Own

 

6

Oil air compressor (8m3 / min)

01

Own

 

7

Hand drill

04

Own

 

8

Punching machine

01

Own

 

9

Pressure compressor + Recorder

01

Rent

 

10

HDD drilling machine

01

Own

 

11

2000L drilling fluid mixer

01

Own

 

12

Drill head locator

01

Rent

 

13

Laser rangefinder

01

Own

 

14

Depth gauge

01

Rent

 

15

Walkie-talkie

03

Own

 

16

Tank trucks carrying clean water

01

Rent

 

17

Tank trucks carrying betone

01

Rent

 

 

 

5.0 TEMPORARY WORKS FOR CONSTRUCTION

- Minh Phuong will transport 01 container 10 ft containing the equipment, tools for construction and other works located at the gathering yard in the construction area.

- Office at the site: at the office of Darco Ba Lai Water Supply Co.Ltd

- Housing of cadres / workers will be rented houses for about 6 km from the construction sites.

- Use 20kVA generator to supply electricity to weld pipes. Water for drilling is provided by tank trucks and portable water tanks.

6.0 DRILL CONSTRUCTION PROGRESS

- Construction progress is calculated from the date the Investor receives the construction approval.

7.0 CONSTRUCTION MATERIAL

The list of main construction materials includes as follows:

Stt

Materials and equipment

Std

Facing

Sch

inch

Unit

Length

1

Pipe HDPE OD560

 

BE

40

 

m

284

2

Pipe HDPE OD355

 

BE

40

 

m

76

3

Pipe HDPE OD225

 

BE

40

 

m

148

 

8.0 DEEP AND SPACE TO UNDERGROUND WORKS

The depth of pipe burying when crossing irrigation canals or ditches is determined based on API RP 1102 standard, input parameters are pipe wall thickness, tunneling depth, parameters of roads and operating vehicles. Check the pipe's stress against allowable stress and weld fatigue against the weld fatigue limit to ensure that the pipe is not damaged or destroyed during operation.

Distance from pipe top to underground works passing through irrigation canals or channels

Stt

Description

Range (m)

Yêu cầu trong CV 5035 /TCĐBVN-QLBTĐB ngày 16/8/2017

1

Distance from HDD borehole to irrigation channel or ditch

- To canal banks, irrigation ditches

- To the scope of the Labor Safety corridor

 

 

 

- 35m

- 32m

 

 

30m (reached)

2

Distance from receiving hole to irrigation canal or ditch

- To canal banks, irrigation ditches

- To the area of the special safety corridor

 

 

 

- 35m

- 40m

 

 

30m (reached)

3

Distance from road surface to top of cage

4

3 (reached)

4

Distance from bottom of drain hose to top of cage

2

Reached

5

Distance from bottom of water supply hose to top of cage

2

Reached

6

Distance from bottom of other underground structures to top of cage

2

Reached

 

 

9.0 CONSTRUCTION METHODS AND DRILLING TECHNICAL SOLUTIONS

9.1 SURVEY

Construction arrangement survey

The construction team, the survey team discussed in reality the ground characteristics, existing obstacles (underground lines, cables, sewers, ...) to determine the location of the drill, the welding position. pipe assembly, towing preparation plan, construction plan for gathering of equipment and materials, possible obstacles and propose solutions to speed up the progress (if necessary).

Thus, it can be seen that the difficulty mainly comes from natural conditions: ground, geographical location, weather. To overcome these difficulties and speed up the progress, the contractor must comply with the following criteria:

1. Mobilizing optimal resources for all stages.

2. Reasonably allocating resources for smooth coordination between the construction sites, local authorities, functional agencies and the Investor, not creating downtime during the construction process.

3. Strictly control, find out potential risks, focus on immediate treatment to prevent these potentials from developing into problems.

9.2 MACHINE EQUIPMENT AND HUMAN RESOURCE

Based on the survey data, Minh Phuong has selected the appropriate equipment and materials to gather to the project. The right and enough selection ensures efficient construction, on schedule and minimizes costs.

Personnel implementing the project must ensure that they have been trained in safety and have specialized certificates relevant to the field in charge.

9.3 PREPARATION OF DRILL work

Using electronic total stations to determine the scope of the construction area in the field.

There are 10 positions to drill through irrigation canals and ditches:

1st underground drilling location - Pipe crossing Vam Ho bridge from pile A25 - A31, HDPE pipe OD560, L = 105m.

 

Liên hệ tư vấn:

CÔNG TY CP TV ĐẦU TƯ VÀ THIẾT KẾ XÂY DỰNG MINH PHƯƠNG

Địa chỉ: Số 28 B Mai Thị Lựu, Phường Đa Kao, Q 1, TPHCM

Chi nhánh: 2.14 Chung cư B1,số 2 Trường Sa, P 17, Q Bình Thạnh, TPHCM

ĐT: (028) 35146426 - (028) 22142126  – Fax: (028) 39118579 - Hotline 090 3649782

Website: www.khoanngam.com;  www.lapduan.com; www.minhphuongcorp.net;

Email: nguyenthanhmp156@gmail.comthanhnv93@yahoo.com.vn

minhphuong corp

 

Bình luận (0)

Gửi bình luận của bạn

Captcha