HDD DRILL CONSTRUCTION PROGRESS
Ngày đăng: 13-03-2021
1,602 lượt xem
TABLE OF CONTENTS
1.2 GENERAL INFORMATION ABOUT THE WORKS
2.0 PREPARATION OF CONSTRUCTION
5.0 TEMPORARY WORKS FOR CONSTRUCTION
6.0 DRILL CONSTRUCTION PROGRESS
8.0 DEEP AND SPACE TO UNDERGROUND WORKS
9.0 CONSTRUCTION METHODS AND DRILLING TECHNICAL SOLUTIONS
9.2 MACHINE EQUIPMENT AND HUMAN RESOURCE
9.7 CLEANING AND RETURNING WORK
10.0 MEASURES OF SAFETY, ENVIRONMENT, SAFETY AND SECURITY OF THE Site
10.4 EXPLOSION OF FIRE PREVENTION, INTERNAL TRANSPORT SAFETY
Project name: Construction of pipeline network
Under the project: Darco Ba Lai Clean Water Factory.
Type of project, grade of project: Group B project, Water pipe work, Level II.
Location: Tan My commune, Ba Tri district, Ben Tre province.
The purpose of this document is to provide a method for the Contractor to perform and control the construction of the pipeline network at the locations as attached in the attached drawing, under the project "DARCO BA LAI CLEAN WATER FACTORY".
- Law on Construction No. 50/2014 / QH 13 dated June 18, 2014 of the 13th National Assembly session;
- Law on Environmental Protection No. 55/2014 / QH13 passed on 23/06/2014 takes effect from 01/01/2015 of the 13th National Assembly session 7;
- Decree No. 59/2015 / ND-CP dated June 18, 2015 of the Government on management of construction investment projects;
- Decree No. 42/2017 / ND-CP dated April 5, 2017 of the Government amending and supplementing a number of articles of Decree No. 59/2015 / ND-CP dated June 18, 2015 of the Government on construction investment project management;
- Decree No. 46/2015 / ND-CP dated 12/5/2015 of the Government on quality management and construction maintenance;
- Decree No. 11/2010 / ND-CP dated February 24, 2010 of the Government regulating the management and protection of road traffic infrastructure;
- Circular No. 50/2015 / TT-BGTVT dated September 23, 2015 of the Ministry of Transport on "Guiding the implementation of a number of articles of Decree No. 11/2010 / ND-CP dated February 24, 2010 .
- Pursuant to Decree No. 32/2015 / ND-CP dated March 25, 2015 on construction cost management;
Investor |
: |
DARCO BA LAI WATER SUPPLY CO.LTD |
Consulting |
: |
ARTELIA VIET NAM CO.LTD |
Project |
: |
DARCO BA LAI CLEAN WATER FACTORY |
Package |
: |
Design, Fabrication and Construction, Installation |
The preparation work was done according to the construction of the whole pipeline.
List of personnel involved in underground drilling construction:
STT |
First and last name |
Date of birth |
ID number |
Home town |
Position |
1 |
Nguyen Văn Thanh |
6/5/1970 |
038070006601 |
Thanh Hoa |
Director – commandant |
2 |
Tran Anh Tuan |
13/06/1972 |
273136899 |
Ha Tinh |
Deputy commander |
3 |
Đang Xuan Dien |
7/10/1961 |
024716077 |
Nghe An |
Deputy commander |
4 |
Đang Minh Nhut |
1986 |
025748413 |
Đong Thap |
Deputy commander |
5 |
Đo Thi Kim My |
17/05/1997 |
291141831 |
Tay Ninh |
Secretary |
6 |
Nguyen Ngoc Thanh |
20/03/1992 |
173754257 |
Thanh Hoa |
Captain |
7 |
Nguyen Tien Long |
27/06/1998 |
175023765 |
Thanh Hoa |
Skill |
8 |
Tran Manh Sung |
30/09/1976 |
033076001982 |
Hung Yen |
Drive the drill |
9 |
Au Le Hai |
1973 |
312381178 |
Bac Giang |
Drive the drill |
10 |
Duong Van Minh |
19/04/1987 |
281286071 |
Nghe An |
Accessories Drilling |
11 |
Nguyen Thanh Hung |
03/09/1972 |
038072003565 |
Thanh Hoa |
Accessories Drilling |
12 |
Nguyen Van Sang |
12/081968 |
261623922 |
Thai Nguyen |
Accessories Drilling |
13 |
Vo Xuan Oanh |
30/10/1965 |
181484282 |
Nghe An |
Accessories Drilling |
14 |
Đoan Van Đong |
1/12/1996 |
251064894 |
Lam Đong |
Accessories Drilling |
15 |
Duong Van Đai |
10/10/1999 |
187766885 |
Nghe An |
Accessories Drilling |
16 |
Nguyen Ngoc Noi |
20/11/1970 |
172156753 |
Thanh Hoa |
Accessories Drilling |
17 |
Phan van Truc |
20/03/1977 |
261221690 |
Thai Nguyen |
Accessories Drilling |
18 |
Pham Minh Tuan |
19/05/1976 |
320940871 |
Ben Tre |
Technical staff |
19 |
Đao Minh Tuan |
29/08/1995 |
362427232 |
Can Tho |
Technical staff |
20 |
Nguyen Minh Phung |
09/08//1995 |
301600511 |
Long An |
Technical staff |
According to the construction organization chart of the project that has been approved by the investor
4.0 CONSTRUCTION EQUIPMENT
List of construction equipment:
STT |
Types of machinery |
Amount |
Own / Rent |
Note |
1 |
Crane 40 tons |
01 |
Rent |
|
2 |
Generator 20 kVA |
01 |
Rent |
|
3 |
Excavator 1 m3 |
02 |
Rent |
|
4 |
Welding machine A300 |
5 |
Own |
|
5 |
Grinding and cutting machine Ø150 |
4 |
Own |
|
6 |
Oil air compressor (8m3 / min) |
01 |
Own |
|
7 |
Hand drill |
04 |
Own |
|
8 |
Punching machine |
01 |
Own |
|
9 |
Pressure compressor + Recorder |
01 |
Rent |
|
10 |
HDD drilling machine |
01 |
Own |
|
11 |
2000L drilling fluid mixer |
01 |
Own |
|
12 |
Drill head locator |
01 |
Rent |
|
13 |
Laser rangefinder |
01 |
Own |
|
14 |
Depth gauge |
01 |
Rent |
|
15 |
Walkie-talkie |
03 |
Own |
|
16 |
Tank trucks carrying clean water |
01 |
Rent |
|
17 |
Tank trucks carrying betone |
01 |
Rent |
|
- Minh Phuong will transport 01 container 10 ft containing the equipment, tools for construction and other works located at the gathering yard in the construction area.
- Office at the site: at the office of Darco Ba Lai Water Supply Co.Ltd
- Housing of cadres / workers will be rented houses for about 6 km from the construction sites.
- Use 20kVA generator to supply electricity to weld pipes. Water for drilling is provided by tank trucks and portable water tanks.
- Construction progress is calculated from the date the Investor receives the construction approval.
The list of main construction materials includes as follows:
Stt |
Materials and equipment |
Std |
Facing |
Sch |
inch |
Unit |
Length |
1 |
Pipe HDPE OD560 |
|
BE |
40 |
|
m |
284 |
2 |
Pipe HDPE OD355 |
|
BE |
40 |
|
m |
76 |
3 |
Pipe HDPE OD225 |
|
BE |
40 |
|
m |
148 |
The depth of pipe burying when crossing irrigation canals or ditches is determined based on API RP 1102 standard, input parameters are pipe wall thickness, tunneling depth, parameters of roads and operating vehicles. Check the pipe's stress against allowable stress and weld fatigue against the weld fatigue limit to ensure that the pipe is not damaged or destroyed during operation.
Distance from pipe top to underground works passing through irrigation canals or channels
Stt |
Description |
Range (m) |
Yêu cầu trong CV 5035 /TCĐBVN-QLBTĐB ngày 16/8/2017 |
1 |
Distance from HDD borehole to irrigation channel or ditch - To canal banks, irrigation ditches - To the scope of the Labor Safety corridor |
- 35m - 32m |
30m (reached) |
2 |
Distance from receiving hole to irrigation canal or ditch - To canal banks, irrigation ditches - To the area of the special safety corridor |
- 35m - 40m |
30m (reached) |
3 |
Distance from road surface to top of cage |
4 |
3 (reached) |
4 |
Distance from bottom of drain hose to top of cage |
2 |
Reached |
5 |
Distance from bottom of water supply hose to top of cage |
2 |
Reached |
6 |
Distance from bottom of other underground structures to top of cage |
2 |
Reached |
Construction arrangement survey
The construction team, the survey team discussed in reality the ground characteristics, existing obstacles (underground lines, cables, sewers, ...) to determine the location of the drill, the welding position. pipe assembly, towing preparation plan, construction plan for gathering of equipment and materials, possible obstacles and propose solutions to speed up the progress (if necessary).
Thus, it can be seen that the difficulty mainly comes from natural conditions: ground, geographical location, weather. To overcome these difficulties and speed up the progress, the contractor must comply with the following criteria:
1. Mobilizing optimal resources for all stages.
2. Reasonably allocating resources for smooth coordination between the construction sites, local authorities, functional agencies and the Investor, not creating downtime during the construction process.
3. Strictly control, find out potential risks, focus on immediate treatment to prevent these potentials from developing into problems.
Based on the survey data, Minh Phuong has selected the appropriate equipment and materials to gather to the project. The right and enough selection ensures efficient construction, on schedule and minimizes costs.
Personnel implementing the project must ensure that they have been trained in safety and have specialized certificates relevant to the field in charge.
Using electronic total stations to determine the scope of the construction area in the field.
There are 10 positions to drill through irrigation canals and ditches:
1st underground drilling location - Pipe crossing Vam Ho bridge from pile A25 - A31, HDPE pipe OD560, L = 105m.